  • Process for Connection to Bluewater Power Distribution System

    1. After reviewing the FIT rules and FIT / microFIT rules and reviewing connection availability resources on the IESO Website, the Applicant should consult with Bluewater Power’s FIT/microFIT Team ( This email address is being protected from spambots. You need JavaScript enabled to view it. ) to identify the project connection point.
    2. The Applicant submits an application to the IESO using its online application tool available at http://www.powerauthority.on.ca/FIT.
    3. After proceeding through the IESO process, and at the appropriate time, the Applicant will be required to submit an Application to Connect to Bluewater Power and also enter into a Connection Agreement with Bluewater Power Distribution Corporation. The Applicant is responsible for the connection costs which must be paid in full before work commences.

    Meter configuration and connection costs will be determined through consultation with Bluewater Power Distribution Corporation.

    Please note: Bluewater Power does not utilize in-series metering configurations.

    The Applicant will be paid monthly for the electricity generated. Prices are set by the IESO. A monthly distribution fixed charge will apply to each FIT project, the amount of which will be determined by the Ontario Energy Board.